Together New Orleans’ organizing around one Community Solar project in New Orleans is bringing about changes across four states.
TNO Weekly News, Liana Heath, March 14, 2026
This week, TNO's organizing around one Community Solar project in New Orleans is bringing about changes across four states.
Solar breakthrough ripples across Entergy territory
A map highlights all of Entergy's territories across Louisiana, Mississippi, Texas and Arkansas.
Solar projects across Entergy’s four-state system could move faster thanks to a decision this week tied to TNO’s Community Solar project with the Sisters of the Holy Family.
TNO leaders uncovered a costly barrier while developing the project. Entergy required installation of a Direct Transfer Trip (DTT), an outdated safety system that would have added over $1 million and months of delay.
TNO commissioned a study showing the equipment wasn’t needed for the Sisters’ project. Discussions opened with the City Council and Entergy about whether the rule itself should change; prompting Entergy to revisit their rules for all territories.
At Wednesday’s Climate & Sustainability Committee meeting, Chair Aimee McCarron accelerated the timeline. Local developers will now learn by April, rather than June, whether a DTT will be required for their projects.
The big picture: Thousands of clean energy projects nationwide are stuck in grid interconnection queues while federal incentives expire by 2027. Speeding up approvals is critical to getting new power online; now, it’ll be easier in all of Entergy’s operating regions.